*The workshop on Templates will be due Oct. 28 (the end of Study Week).
*Due dates date for R02 and R03 are is extended **Release BOTH Releases 0.2: and 0.3 will be due on OctNov. 11. 28**If you can deliver both Release 0.2 and Release 0.3: due on before Nov. 4 11, I will award bonus points.
== Week 7 ==
== Study Week ==
 
 
 
*Finish up Assignment 2 Release 0.2, submission due date is Sunday Oct. 28 23:55
 
*Start working on A2 Release 0.3
== Week 8 ==
  *Finish up Continue working on Assignment 2 Release 0.2 and 0.3, submission due date is Sunday Nov. 4 11 23:55
== Week 9 ==