== Project Milestones ==
*'''Milestone 0.0: Exploration of Project Ideas. [Week 1 - Week 3]'''
**Identify an application domain for your Android project.
**Gather information from end users (i.e. people who will use your app).
** Do market research (e.g. Google Play Store) if needed.
*'''Milestone 1.0: Submission of a Project Proposal. [Week 4 - Week 5]'''
** date of submission: '''February 15, 2015'''
** Watch the video (approx. 7 minutes) about creating user stories. [http://scrumtrainingseries.com/BacklogRefinementMeeting/BacklogRefinementMeeting.htm]
*** identify checkpoints/milestones
** Your proposal must include the name of your app, names of team members, and the date of submission.
* '''Milestone 2.0: Design and Implementation. [Week 7 - Week 12 (February 15 - March 31); 6 weeks]'''** Submit*** the REVISED project proposal 2.0*** the Design Report 2.0** GitHub ** Read the design requirements below.** WeeklyGitHub activities
** Weekly standup meetings on Fridays [http://scrummethodology.com/scrum-meetings/]
**# What have I done since the last Scrum meeting (yesterday)?
**# What prevents me from performing my work as efficiently as possible?
** Sprints (i.e. iterations) [http://scrummethodology.com/scrum-sprint/]
* '''Milestone 3.0: Project Presentation and Final Report. [Week 14]'''
** '''April 13, 2015 (Monday)'''
 
== Design Requirements ==
*Create detailed system diagrams.
** UI mockups
** interaction between backend components and the UI screens
** flow of data between the UI screens and data stores such as database and Android file system
** flow of data between the UI screens and Web API servers (URLs), if applicable
*Consult Material Design Guidelines.