Difference between revisions of "BTP300 Team RAAP"

From CDOT Wiki
Jump to: navigation, search
(Project Status)
(Project Status)
 
Line 24: Line 24:
  
 
*Started Assignment 2: Oct 12, 2011
 
*Started Assignment 2: Oct 12, 2011
 
 
*Divided Assignment 2 among team members: Oct 12, 2011
 
*Divided Assignment 2 among team members: Oct 12, 2011
 
 
*Worked on CFrame, drawing the box and capturing the characters the box covers : Renaldo H, Oct 18, 2011
 
*Worked on CFrame, drawing the box and capturing the characters the box covers : Renaldo H, Oct 18, 2011
 
 
*Complied a2test.cpp and all classes successfully : Ari A, Oct 26, 2011
 
*Complied a2test.cpp and all classes successfully : Ari A, Oct 26, 2011
 
 
*Completed CFrame.cpp and CFrame.h : Ari A, Oct 28, 2011
 
*Completed CFrame.cpp and CFrame.h : Ari A, Oct 28, 2011
 
*Assignment 2 completed
 
*Assignment 2 completed
 +
  
 
Assignment 3
 
Assignment 3

Latest revision as of 15:08, 13 November 2011


BTP300 Fall 2011 | Weekly Schedule | Student List | Project Requirements | Teams and their Projects | Student Resources

RAAP

Repository

SVN Repository link: svn://zenit.senecac.on.ca//btp300_113rep7

Repo ID

btp300_113rep7

Trunk Status

  • Added Assignment 1 to trunk folder: committed by Archana
  • Added Assignment 2 to tags and trunk folder: committed by Archana

Team Members

  1. Renaldo
  2. Archana Sahota
  3. Ari Azar
  4. Pradeep Waragoda

Email All

Project Status

Assignment 2

  • Started Assignment 2: Oct 12, 2011
  • Divided Assignment 2 among team members: Oct 12, 2011
  • Worked on CFrame, drawing the box and capturing the characters the box covers : Renaldo H, Oct 18, 2011
  • Complied a2test.cpp and all classes successfully : Ari A, Oct 26, 2011
  • Completed CFrame.cpp and CFrame.h : Ari A, Oct 28, 2011
  • Assignment 2 completed


Assignment 3

  • Divided Assignment 3 among team members: Nov 11, 2011

Resources