Started Assignment 2: Oct 12, 2011
 
  
Divided Assignment 2 among team members: Oct 12, 2011
+
Assignment 2
  
Worked on CFrame, drawing the box and capturing the characters the box covers : Renaldo H, Oct 18, 2011
+
*Started Assignment 2: Oct 12, 2011
  
Complied a2test.cpp and all classes successfully : Ari A, Oct 26, 2011
+
*Divided Assignment 2 among team members: Oct 12, 2011
  
Completed CFrame.cpp and CFrame.h : Ari A, Oct 28, 2011
+
*Worked on CFrame, drawing the box and capturing the characters the box covers : Renaldo H, Oct 18, 2011
 +
 
 +
*Complied a2test.cpp and all classes successfully : Ari A, Oct 26, 2011
 +
 
 +
*Completed CFrame.cpp and CFrame.h : Ari A, Oct 28, 2011
 +
*Assignment 2 completed
 +
 
 +
Assignment 3
 +
 
 +
*Divided Assignment 3 among team members: Nov 11, 2011
  
 
== Resources ==
 
== Resources ==

Revision as of 15:08, 13 November 2011


BTP300 Fall 2011 | Weekly Schedule | Student List | Project Requirements | Teams and their Projects | Student Resources

RAAP

Repository

SVN Repository link: svn://zenit.senecac.on.ca//btp300_113rep7

Repo ID

btp300_113rep7

Trunk Status

  • Added Assignment 1 to trunk folder: committed by Archana
  • Added Assignment 2 to tags and trunk folder: committed by Archana

Team Members

  1. Renaldo
  2. Archana Sahota
  3. Ari Azar
  4. Pradeep Waragoda

Email All

Project Status

Assignment 2

  • Started Assignment 2: Oct 12, 2011
  • Divided Assignment 2 among team members: Oct 12, 2011
  • Worked on CFrame, drawing the box and capturing the characters the box covers : Renaldo H, Oct 18, 2011
  • Complied a2test.cpp and all classes successfully : Ari A, Oct 26, 2011
  • Completed CFrame.cpp and CFrame.h : Ari A, Oct 28, 2011
  • Assignment 2 completed

Assignment 3

  • Divided Assignment 3 among team members: Nov 11, 2011