Created page with '<-- Go Back == <u>'''Accomplishments'''</u> == <u>''' Week 2: Oct 13 - 19 '''</u> * Wednesday: meeting and deciding what part each of the team me…'
[[BTP300B A2 Teams Fall 2013|<-- Go Back]]

== <u>'''Accomplishments'''</u> ==

<u>''' Week 2: Oct 13 - 19 '''</u>
* Wednesday: meeting and deciding what part each of the team members will do


<u>''' Week 3: Oct 20 - 26 '''</u>
* Friday:
** All team members finished their coding tasks.
** Meeting in order to decide what will be the future steps.
** Future steps are:
*** Due to segmentation fault during testing we decided that each of team members will test at home in order to find what causes the fault.


<u>''' Week 4: Oct 27 - Nov 2'''</u>
* Monday:
** The cause for the segmentation fault was found (will be presented in the bug report below).
** The fix was shared between team members using SVN for future testing and improving of the program.
** So far, our code compiles, executes, but the output we get does not looks exactly like required.


== <u>'''Bugs/Problems'''</u> ==

<u>''' Week 3: Oct 20 - 26 '''</u>
* Friday:


<u>''' Week 4: Oct 27 - Nov 2'''</u>