Project Process
| IO_Field ||Xiaozhe || Nov 25 || Done
|-
| IO_Form || Zhaolong || Nov 25 || -Done
|-
| IO_Frame || Dong || Nov 25 || Done
| IO_Vedit || Keyan || Nov 25 || Done
|-
| IO_CheckList || Fardad (bug fixed) || - || Done
|-
| IO_Menu || Fardad (bug fixed) || - || Done
|-
| IO_TextEditor || Feihong / Xiaozhe || Nov 25 || -Done
|-
| Main || Suwon || Nov 25 || -
|}
 
==Meeting Schedule==
1. '''Congratulations! Good job everyone!''' Our version is finally working after all of us have worked hard for this project.
 
2. We will have a meeting this week at 9 pm Fri.(Dec 4)
 
3. The final due date is Dec 8.
 
4. '''Good luck''' on your tests, quiz, and final exam.
==Project Suggestions==
''' 5. Eliminate warnings as many as possible.'''
==LOG======dsun17==Project Process==
====fxiong1====1. Oct 23, 2009 -- We start doing our project, and everyone is assigned a class to work on.
====kren1====2. Oct 27, 2009 -- The first IRC class. We post ciol.h and ciol.cpp on our repo, then, Fardad write prjmain.cpp for us
====suwon====3. Oct 30, 2009 -- Group meeting
====xshi18====4. Nov 06, 2009 -- Group meeting
====zlzhu====5. Nov 13, 2009 -- Group meeting
==Meeting Schedule==16. We will have two meetings this week at 9 pm on WedNov 14, 2009 -- All the classes were finished.(Nov 25) Fixing bugs after putting all the classes and Frisample main together. 7.(Nov 27)20, 2009 -- Group meeting
28. We need to make our project at least work before Nov 28.25, 2009 -- Group meeting
3. The final due date changed to Dec 89.Nov 27, 2009 -- Group meeting
10. Nov 30, 2009 -- Our project works very well. Waiting the final version of main to be posted.
== Meeting Minutes ==
All the classes will be done by Wed. (Nov 25)
IO_vedit has be been submitted.
Feihong is working on texteditor.
An is working on main.
 
'''6. Nov 25, 2009'''
Time: 9 to 10 pm
Present: Keyan, [Frank]Dong, Feihong, An, [Lucy]Xiaozhe, Zhaolong
 
IO_textedit has been submitted.
IO_form has been submitted.
 
All classes are uploaded on svn.
The next stage is to eliminate bugs.
 
'''7.Nov 27, 2009'''
Time: 9 to 10 pm
Present: Keyan, [Frank]Dong, Feihong, An, [Lucy]Xiaozhe, Zhaolong
 
All classes are done. We discussed some functions in IO_Form. After we had compiled all the classes with main, there were some problems in IO_Form::edit(), IO_edit, and IO_label. Frank will send an email to Fardad and describe the problems.
 
'''8.Dec 04, 2009'''
Time: 9 to 10:30 pm
Present: Keyan, [Frank]Dong, Feihong, An, [Lucy]Xiaozhe
 
Frank found a bug in our project. bug: when you type in a invalid date and press down key, it should show the error message and stop at the field, but it actually jumps to the next field. The bug may hide in Form class.
 
we start a new project. An will write a Vedio shop Main function, so we can test our classes on the new project main function.