Open main menu

CDOT Wiki β

Changes

BTP300A Team 42 Weekly Log

348 bytes added, 19:37, 22 September 2012
no edit summary
*9/17 (Monday): Demo of program in class (done).
*9/17 (Monday): Pair programming over Skype (1hr). Smart text-wrap working.
*9/18 (Tuesday): Pair Programming in the Open Lab (1hr). Finished up sample Worked on main.*9/21 (Friday): Pair Programming in Computer Lab (4hrs). Worked on main. *9/21 (Friday): Pair Programming over Skype (2hrs). Colors and cross-platform compatibility done. *9/22 (Saturday): Pair Programming over Skype (3hrs). Added clock and cursor features to main.  *9/22 (Saturday): Prepared typescript / screenshots / binaries for submission. (Done) 
==Week 4 ==