Open main menu

CDOT Wiki β

BTP300B Team 3 Weekly Log

Revision as of 19:33, 4 November 2012 by Wesley Christopher Hamilton (talk | contribs) (Week 6)

Week 1

  • 10/09/2012: Reviewed the console readings and read A1. Consulted Peter on certain questions and updated the Q&A on one of them.

Week 2

  • 23/09/2012: Worked every day on the assignment. finally at 11:30 sunday night got all the screenshots finished. thank you people in the Q&A for the tip on putty with END and HOME

=3

Week 3

  • 25/09/2012: started work on A2, planned out the functions

Week 4

  • 06/10/2012: Worked every day on the functions, completing them little by little. Almost done =)

Week 5

  • 10/10/2012: Got help and finished the assignment =D

Week 6

  • 10/15/2012: Assigned function roles:
    Alex: CLabel
    Wesley: CButton
    Joe: CLine
    Daniel: CField

Setup and recieved SVN Instructions:

Week 7

  • 10/24/2012: It's been study week for a couple days now, working on setting up everyone on SVN and hopefully get a decent amount of work done by the end of the week

Week 8

Week 9

Week 10

Week 11

Week 12

Week 13

Week 14