Week 1

1/12/2011 (Wed)  NexJ project team meeting

1/15/2011 (Sat)   Research Notes

Week 2

1/18/2011 (Tue)

1/19/2011 (Wed)

  • NexJ project team meeting
    • The PostgreSQLAdapter project must be completed by March 31, 2011.
    • New projects will be proposed to NexJ for approval.
  • Research Notes

1/20/2011 (TH)

  • NexJ Coding Standards received from Grace
  • Code base for the PostgreSQLAdapter project checked out from the mercurial repository
    • build errors encountered

Week 3