Remaining software installations.
 +
 +
Meeting for defining main goals. Detailed prototype review; first tasks assigned, and database changes discussed.
 +
 +
First task started: software downloaded and successfully installed.
  
 
||
 
||
Line 80: Line 86:
 
|-
 
|-
 
| Friday ||
 
| Friday ||
 +
Work in progress on the first main task.
 +
Main software tools integration was tested (eclipse IDE and Tomcat server) with a small JSP project, which includes a connection with a MySQL database, running on Tomcat server.
  
 
||
 
||

Revision as of 14:17, 17 June 2013


BigBlueButton | BBB Weekly Log
Bo | Chad | Gary | Justin | Robert | Ystallonne

Logs for 20132

Blog

Please add the daily logs (Latest week at the top of the page)

Week of June 3rd

Week Day Today's work Blog URL(At least One)
Monday
Tuesday
Wednesday

Set up of workspace environment.

Installation of OS and necessary software tools.

Short meeting for reviewing prototype.

Link

Thursday
Friday
Saturday


Week of May 27th

Week Day Today's work Blog URL(At least One)
Monday
Tuesday
Wednesday

Set up of workspace environment.

Installation of OS and necessary software tools.

Short meeting for reviewing prototype.

Link

Thursday

Remaining software installations.

Meeting for defining main goals. Detailed prototype review; first tasks assigned, and database changes discussed.

First task started: software downloaded and successfully installed.

Friday

Work in progress on the first main task. Main software tools integration was tested (eclipse IDE and Tomcat server) with a small JSP project, which includes a connection with a MySQL database, running on Tomcat server.