Revision as of 21:35, 14 September 2012
Contents
Week 1
9/10/2012
Rubinder started with pair programming, read and tested Assignment 1
Radney started with pair programming, read and tested Assignment 1
9/13/2012
Radney got the display function to display the string depending on field length
Did pair programming in the Open lab and finished the display function
OFF CLASS COLLABORATION
9/13/2012
Rubinder - Worked on the edit function, got the left,right,home,end keys working. Got the cursor to stay within the field, but no scrolling yet.