Revision as of 21:12, 25 January 2011
Week 1
1/12/2011 (Wed) NexJ project team meeting
1/15/2011 (Sat) Research Notes on the SQLAdapter class
Week 2
1/18/2011 (Tue)
1/19/2011 (Wed)
- NexJ project team meeting
- The PostgreSQLAdapter project must be completed by March 31, 2011.
- New projects will be proposed to NexJ for approval.
- Research Notes on the SQLSchemaManager class
1/20/2011 (TH)
- NexJ Coding Standards received from Grace
- Checkd out the code base of the PostgreSQLAdapter project from the mercurial repository
- build errors encountered
Week 3
1/24/2011 (Mon)
- Ran the JUnit test PostgreSQLSchemaManagerTest.
- errors encountered
1/25/2011 (Tue)
1/26/2011 (Wed)
- NexJ team meeting