Difference between revisions of "User:Gbatumbya/tasklist/2010July"
< User:Gbatumbya | tasklist
(→Week 2) |
(→Week 2) |
||
Line 22: | Line 22: | ||
'''8 Thur''' | '''8 Thur''' | ||
* Rebuild NexJ Express in new environment | * Rebuild NexJ Express in new environment | ||
− | * Completed Project Plan | + | * Completed Project Plan |
* Continued reading NexJ code (understanding Transfer Objects) | * Continued reading NexJ code (understanding Transfer Objects) | ||
− | * Work on Project Page on wiki | + | * Work on Project Page on wiki [http://zenit.senecac.on.ca/wiki/index.php/NexJExpress] |
'''9 Fri''' | '''9 Fri''' |
Revision as of 16:17, 8 July 2010
Week 1
1 Thur
- Statutory Holiday
2 Fri
- Campus closed
Week 2
5 Mon
- Writing Project Plan for NexJ Studio JSON Adapter
- Read about WADL and WSDL [1]
6 Tue
- Writing Project Plan for NexJ Studio JSON Adapter
- Coding Utility class JSONWriter
7 Wed
- Continued with Project Plan
- Met with Jordan to review Project Plan
- Continued reading NexJ code
8 Thur
- Rebuild NexJ Express in new environment
- Completed Project Plan
- Continued reading NexJ code (understanding Transfer Objects)
- Work on Project Page on wiki [2]
9 Fri