Difference between revisions of "Winter 2009 SYA810 Weekly Schedule"
Chris Tyler (talk | contribs) (Initial schedule) |
Chris Tyler (talk | contribs) |
||
Line 4: | Line 4: | ||
*** 7 releases, every 2 weeks | *** 7 releases, every 2 weeks | ||
*** Developing a Release Roadmap | *** Developing a Release Roadmap | ||
− | = Week 2 (January 19) - Advanced storage I: RAID = | + | = Week 2 (January 19) - Advanced storage I: RAID and LVM-on-RAID = |
= Week 3 (January 26) - Release 0.4 = | = Week 3 (January 26) - Release 0.4 = | ||
− | = Week 4 (February 2) - Advanced storage II = | + | = Week 4 (February 2) - Advanced storage II SANs and iSCSI = |
= Week 5 (February 9) - Release 0.5 = | = Week 5 (February 9) - Release 0.5 = | ||
− | = Week 6 (February 16) = | + | = Week 6 (February 16) - Performance Turning = |
= Week 7 (February 23) - Release 0.6 = | = Week 7 (February 23) - Release 0.6 = | ||
= Study Week (March 2) = | = Study Week (March 2) = | ||
= Week 8 (March 9) - Release 0.7 = | = Week 8 (March 9) - Release 0.7 = | ||
− | = Week 9 (March 16) = | + | = Week 9 (March 16) - Backup and Restore I = |
= Week 10 (March 23) - Release 0.8 = | = Week 10 (March 23) - Release 0.8 = | ||
− | = Week 11 (March 30) = | + | = Week 11 (March 30) - Backup and Restore II = |
= Week 12 (April 6) - Release 0.9 = | = Week 12 (April 6) - Release 0.9 = | ||
− | = Week 13 (April 13)= | + | = Week 13 (April 13) - Project Poster Sessions (Tentative) = |
= Exam Week (April 20) - Release 1.0 = | = Exam Week (April 20) - Release 1.0 = |
Revision as of 11:09, 6 January 2009
Contents
- 1 Week 1 (January 12) - Release Planning & Roadmap
- 2 Week 2 (January 19) - Advanced storage I: RAID and LVM-on-RAID
- 3 Week 3 (January 26) - Release 0.4
- 4 Week 4 (February 2) - Advanced storage II SANs and iSCSI
- 5 Week 5 (February 9) - Release 0.5
- 6 Week 6 (February 16) - Performance Turning
- 7 Week 7 (February 23) - Release 0.6
- 8 Study Week (March 2)
- 9 Week 8 (March 9) - Release 0.7
- 10 Week 9 (March 16) - Backup and Restore I
- 11 Week 10 (March 23) - Release 0.8
- 12 Week 11 (March 30) - Backup and Restore II
- 13 Week 12 (April 6) - Release 0.9
- 14 Week 13 (April 13) - Project Poster Sessions (Tentative)
- 15 Exam Week (April 20) - Release 1.0
Week 1 (January 12) - Release Planning & Roadmap
- Course overview and plan
- Project Release schedule
- 7 releases, every 2 weeks
- Developing a Release Roadmap
- Project Release schedule