Accomplishments

Week 2: Oct 13 - 19

  • Wednesday: meeting and deciding what part each of the team members will do


Week 3: Oct 20 - 26

  • Friday:
    • All team members finished their coding tasks.
    • Meeting in order to decide what will be the future steps.
    • Future steps are:
      • Due to segmentation fault during testing we decided that each of team members will test at home in order to find what causes the fault.


Week 4: Oct 27 - Nov 2

  • Monday:
    • The cause for the segmentation fault was found (will be presented in the bug report below).
    • The fix was shared between team members using SVN for future testing and improving of the program.
    • So far, our code compiles, executes, but the output we get does not looks exactly like required.


Bugs/Problems

Week 3: Oct 20 - 26

  • Friday:


Week 4: Oct 27 - Nov 2

  • Monday: